« Donate Canned Food to Victims of the Pakistan Flood | Main | Pesticide Spraying Notification to Reduce Mosquito Activity in Brooklyn »
Changes to B and Q Train Service due to Brighton Line Rehabilitation Project
| Posted on: August 24, 2010 |
The MTA has informed CB14 of the following changes to Brighton Line Subway Service due to the rehabilitation project:
This is to inform you that MTA NYC Transit will be operating shuttle buses along the Brighton B/Q subway line from Prospect Park to Stillwell Avenue during three upcoming weekends, due to the ongoing station rehabilition projects from Newkirk Avenue to Kings Highway along the line. Shuttle buses will service all stations between Prospect Park and Stillwell Avenue, and NYC Transit personnel will be available to assist our customers in utilizing the alternate service. Posters will be placed at each affected station in advance of each weekend, and updated information will be available on our website at www.mta.info
The weekends when shuttle buses will replace trains (from 12:01 a.m. Saturdays through 5:00 a.m. Mondays are:
September 11-13
September 25-27
October 2-4 (this is currently a backup weekend and will be needed only if all work is not completed during the first two weekends)
Topics: Transportation